How did China build vulcan mountain hospital in a week

On January 23, Huoshenshan hospital was launched. the hospital is 33,900 square meters, with 1,000 beds. The hospital also has an intensive care unit, an intensive care unit and an ordinary unit.

Personnel and equipment quickly assembled overnight on New Year's eve

On New Year's eve, 95 excavators, 33 bulldozers, 5 road rollers, 160 dump trucks, more than 400 workers rushed into the site to level the mountain.In the face of this challenge, on the one hand, the builder arranged the material procurement team to feedback the material equipment to the design institute at the first time, and asked it to make drawings according to the existing material equipment. On the other hand, special arrangement of installation process is used to offset the impact of specification difference.

The major enterprises work closely with each other to provide mobility

At the same time in the construction project, the relevant enterprises on the one hand to do a good supporting and support, on the one hand for some sudden needs, to provide mobile power.

Prior to the formal delivery of Huoshenshan hospital, China telecom has fully completed the construction of the hospital's fixed-line telephone, optical fiber, 4G and 5G network coverage, medical cloud access, remote consultation and other information systems.Based on the high-performance 5G network, China telecom and CGV jointly launched "epidemic 24 hours", which carried out full hd live broadcast of the construction of two hospitals in Huoshenshan and Leishenshan, and at the same time watched more than 80 million online users.

Strict standards are applied to ensure that pollutants do not permeate the soil and water bodies

While making sure it was "fast", Huoshenshan hospital was "good enough".

Huoshenshan hospital adopts the form of field hospital, special space arrangement, the patients and medical staff activity space for effective isolation, the formation of negative pressure airflow in the air tissue, to avoid the cross-infection with air as the medium.Vulcan mountain hospital laid 50,000 square meters of anti-seepage film, covering the entire hospital area, to ensure that pollutants will not permeate the soil and water, and installed rainwater, sewage treatment system, after two chlorine disinfection treatment, can be discharged into the municipal pipe network.Each ward in the hospital is separately equipped with a non-circulating fresh air system and an exhaust air system, which together constitute a negative pressure system to maintain a continuous supply of fresh air to the ward. In addition, the hospital has set up a garbage incinerator on the south side of ward 1 building.